Dry docking and undocking process map
A swimlane map of dry-docking a vessel from block-plan approval to refloat, across the Dock Master, Planning, Mechanical, QA/QC and the vessel/customer. It carries four decision points because dry-docking is the one procedure in a yard where getting a check wrong can mean structural damage to the vessel, not just a schedule slip.
Opens a copy in the editor and saves it in this browser. No account, nothing sent anywhere.
What is in this map
20 steps across 5 swimlanes and 4 phases, with 4 decision points.
- Swimlanes (who does the work)
- Dock Master, Planning, Mechanical, QA/QC and Vessel / customer
- Phases (left to right)
- Dock preparation, Docking, Dry period and Undocking and departure
Why map this process
Every one of this map's four decisions exists because the alternative is checking a box and hoping. The block plan has to match the vessel's actual keel and bilge profile before a single block is positioned; the vessel has to be centered and within trim tolerance before dewatering starts; block landing has to be verified once dry, with a re-flood-and-re-land loop if it is not. A checklist can ask the same three questions, but only the map shows that each is a gate a vessel cannot pass through on the strength of the step before it.
The dry period is where most of the actual repair work happens, and the map deliberately keeps it as one authorize-then-monitor loop rather than expanding into every trade's own work. That is correct: this map's job is to control entry to and exit from the dry dock, not to plan the repairs inside it — that is what the individual repair and inspection maps in this cluster are for.
Every step in the map
This is the spreadsheet behind the diagram. The numbers in “Goes to” are row numbers, which is exactly what the editor’s “Line to” column holds — so you can read the flow here and retype any part of it.
| # | Step | Shape | Swimlane | Phase | Goes to |
|---|---|---|---|---|---|
| 1 | Docking date confirmed on the dock schedule | Start | Planning | Dock preparation | 2 |
| 2 | Prepare block plan against vessel's docking drawing | Document | Dock Master | Dock preparation | 3 |
| 3 | Block plan matches *keel and bilge* profile? | Decision | Dock Master | Dock preparation | 5 (Yes), 4 (No) |
| 4 | Revise block layout with vessel's chief engineer | Process | Dock Master | Dock preparation | 3 |
| 5 | Position keel and bilge blocks in the dock | Process | Mechanical | Docking | 6 |
| 6 | Position vessel over blocks under pilotage | Process | Dock Master | Docking | 7 |
| 7 | Vessel centered and *trim* within tolerance? | Decision | Dock Master | Docking | 9 (Yes), 8 (No) |
| 8 | Reposition vessel with tugs and winches | Process | Dock Master | Docking | 7 |
| 9 | Begin **controlled dewatering** of the dock | Process | Dock Master | Dry period | 10 |
| 10 | Monitor block landing as the waterline drops | Process | Mechanical | Dry period | 11 |
| 11 | Verify **vessel stability** and block contact once dry | Control | QA/QC | Dry period | 12 |
| 12 | Vessel **stable and correctly landed** on blocks? | Decision | QA/QC | Dry period | 14 (Yes), 13 (No) |
| 13 | Re-flood partially and re-land vessel on blocks | Process | Dock Master | Dry period | 11 |
| 14 | **Authorize** repair teams to enter the dry dock | Approval | Planning | Dry period | 15 |
| 15 | Repair work proceeds through the dry period | Subprocess | Mechanical | Dry period | 16 |
| 16 | **All dry-dock work complete** and dock clear? | Decision | Planning | Undocking and departure | 18 (Yes), 17 (No) |
| 17 | Extend dry period and notify customer of revised schedule | Process | Planning | Undocking and departure | 15 |
| 18 | Flood the dock and **refloat the vessel** | Process | Dock Master | Undocking and departure | 19 |
| 19 | Final underwater checks and customer walk-through | Process | Vessel / customer | Undocking and departure | 20 |
| 20 | Vessel refloated and departs the dry dock | End | Vessel / customer | Undocking and departure | End |
The decision points
Every branch in the map, with the label on each outgoing line. These are the questions the process has to be able to answer.
-
3. Block plan matches *keel and bilge* profile?
Owned by Dock Master · Dock preparation
- Yes → step 5
- No → step 4
-
7. Vessel centered and *trim* within tolerance?
Owned by Dock Master · Docking
- Yes → step 9
- No → step 8
-
12. Vessel **stable and correctly landed** on blocks?
Owned by QA/QC · Dry period
- Yes → step 14
- No → step 13
-
16. **All dry-dock work complete** and dock clear?
Owned by Planning · Undocking and departure
- Yes → step 18
- No → step 17
Notes on specific steps
These notes travel with the map. In the editor they live in the Notes column and appear when you open a box.
- 2. Prepare block plan against vessel's docking drawing
- Built from the vessel's own docking plan, not a generic layout — keel blocks, bilge blocks and any hull penetrations or sea chests that need to clear a block entirely.
- 9. Begin **controlled dewatering** of the dock
- Pumped down in stages, not in one continuous run, so the block landing can be watched and stopped the moment something looks wrong.
- 15. Repair work proceeds through the dry period
- Every discipline's dry-dock-only work — hull, sea valves, propeller, rudder — has to close out here, because none of it is reachable once the dock floods again.
Making it yours
The controlled-dewatering step and its Notes column are where your yard's own procedure differs most from another's: how many stages you pump down in, and what 'monitor block landing' actually means in practice, belongs there rather than as a new row, because it is guidance for the person doing the step, not a separate action. If your dock uses a different verification method for stability, rename the row and keep its two branches — the decision after it is what makes a bad landing correctable rather than something discovered only when the dock reopens.
What to watch out for
- Do not merge the block-plan decision with block positioning. One is a paper check against the vessel's docking drawing; the other is physical placement in the dock. Merging them removes the only place a wrong block layout is caught before the vessel is actually sitting on it.
- The stability-and-landing decision has a re-flood branch, not just a fail branch. If you draw it as a dead end, the map implies a bad landing means starting the whole dry-docking process over, when the actual response is a partial re-flood and a re-land — a much shorter loop back.
- 'All dry-dock work complete' has to be a real gate, not a formality. Extending the dry period is the row that protects the customer's schedule commitment from a trade that quietly runs long — deleting it means the map has no honest way to say the dock stayed occupied longer than planned.
Frequently asked questions
Why is there a separate decision for the block plan AND for the vessel being centered?
Because they can fail independently. A correct block plan can still be badly executed if the vessel is not centered and trimmed correctly over it — the blocks can be right and the vessel's position over them can still be wrong. Keeping both as separate decisions is what lets the map show which one actually failed when a docking does not go cleanly.
How do I add a separate step for underwater hull inspection during the dry period?
Give it its own row inside the dry-period phase, in whichever lane owns it — usually Mechanical, or a QA/QC row if it is a formal inspection. Point the 'all dry-dock work complete' check at it as one of the items being verified, so that gate cannot pass without it.
Does this map cover the vessel's own crew's responsibilities during dry-docking?
Only where they intersect the yard's process — the customer walk-through near the end. If your yard needs the vessel's crew to sign off on specific systems before departure, add a decision after that walk-through rather than folding crew sign-off into the yard's own final checks; it is a different party with a different authority to withhold.
Open the map and start editing
The editor loads this chart with the spreadsheet underneath it. Change a cell and the diagram redraws — no drawing, no signup.